Koryx Copper values Namibia’s Haib project at $2.5 billion as report confirms 24-year mine life

Feyisayo Ajayi
Feyisayo Ajayi
Haib copper project

Koryx Copper S.A., the Luxembourg-domiciled mining and exploration company focused on advancing major copper assets in Africa, has reported a post-tax net present value of $2.5 billion for its wholly owned Haib Copper Project in southern Namibia, following completion of a pre-feasibility study outlining a 24-year open-pit mining operation.

The study estimates a post-tax internal rate of return of 25% at a base-case copper price of $5 per pound, alongside an upfront development capital requirement of $2.06 billion. The project is expected to produce an average of 135,000 tonnes of copper annually during its first 10 years, with additional revenue from gold and molybdenum.

The assessment also identifies an after-tax net present value of $3.875 billion and an internal rate of return of 32.2% under a higher copper-price scenario of $13,000 per tonne, compared with the base-case valuation of $2.538 billion.

Haib project targets large-scale copper production

Under the PFS, Haib is projected to deliver average annual payable copper production of 130,000 tonnes during its first decade, declining to 105,000 tonnes over the mine’s full life. Average annual payable gold production is estimated at 15,000 ounces in the first 10 years, while payable molybdenum output is expected to reach 1.22 million pounds annually.

The project is designed around a conventional open-pit mining operation and a 48-million-tonne-per-year processing plant. Its proposed processing route combines three-stage crushing, high-pressure grinding rolls, ball milling and a flotation circuit incorporating Jameson and mechanical tank cells.

Koryx Copper estimates a first-decade C1 cash cost of $1.72 per pound of payable copper and an all-in sustaining cost of $2.07 per pound. Across the mine’s life, these costs are projected to rise to $2.19 and $2.52 per pound, respectively.

The study estimates total copper production of about 2.61 million tonnes over the mine life, with copper recovery averaging 89.5% during the first decade and 87.3% over the full operating period.

Mineral reserves underpin 24-year development plan

The updated resource estimate identifies 4.35 million tonnes of contained copper across indicated and inferred resources. The project also has probable mineral reserves of approximately 1.12 billion tonnes of ore grading 0.27% copper, containing nearly 3 million tonnes of copper, alongside molybdenum and gold.

Mining is expected to run for about 15 years, followed by processing reclaimed low-grade stockpiles through the final years of the operation. The mine plan includes 1.12 billion tonnes of ore and 1.09 billion tonnes of waste, with an overall strip ratio of 0.98:1.

Koryx Copper has also incorporated a hybrid electricity supply system comprising a 220-kilovolt connection to NamPower’s Harib substation, approximately 417 megawatts-peak of solar capacity and 361 megawatt-hours of battery storage. 

The renewable component is expected to supply about 45% of the project’s electricity requirements over its life.

Water supply is planned from the Orange River, with annual demand estimated at 20 million cubic metres and an off-channel storage dam proposed to manage seasonal availability.

Koryx advances feasibility and permitting

Koryx Copper, listed on the Toronto Stock Exchange (TSX) Venture Exchange and Namibia Securities Exchange, is advancing major copper assets in Africa. Its flagship project is the 100%-owned, PEA-stage Haib Copper Project in southern Namibia, one of the largest porphyry copper deposits in Africa and it is also expanding its exploration portfolio in Zambia. Haib is designed as a large open-pit sulphide flotation operation with projected average annual production of about 92,000 tonnes of copper over a 24-year mine life.

Koryx Copper plans to begin a definitive feasibility study in early 2027, targeting completion within approximately one year. The work will refine engineering designs, metallurgical performance, capital and operating costs, and the mineral reserve base before project financing and a construction decision.

The company is targeting completion of major permits, including the mining licence and environmental clearance, by mid-2027. It expects early construction works to begin by the end of 2027, with full construction targeted for the first quarter of 2028.

Commenting on the results, president and chief executive Heye Daun said the PFS had exceeded the company’s initial expectations, positioning Haib as a major copper development project in Namibia. He said the next 12 months would focus on completing the definitive feasibility study, securing financing and advancing permitting ahead of construction.

Koryx Copper will discuss the PFS results during an online investor webinar on November 18, 2026, at 10:00 a.m. Eastern Time, corresponding to 5:00 p.m. in Namibia. The company also plans an on-site investor day on February 4 and 5, 2027.