Kavango Resources expands power capacity at Zimbabwe gold project

Oluwatosin Alao
Oluwatosin Alao
Kavango Resources

Kavango Resources has completed a fivefold expansion of electricity capacity at its Hillside gold project in Zimbabwe, strengthening the infrastructure behind its plans to increase gold processing and improve operating efficiency. 

The mining company has energised a new 1 MVA transformer, taking installed capacity at Hillside from 250 kVA to 1.25 MVA.

The upgrade gives the operation direct access to grid electricity, with Kavango expecting more stable power supplies and lower energy costs.

Power upgrade targets production costs 

The investment addresses one of the operational requirements facing gold producers seeking to increase output: securing dependable electricity without allowing energy expenses to erode production economics. 

Kavango expects the new connection to improve power reliability while reducing the cost of supplying electricity to its Hillside operations. 

The timing is significant for the project. The transformer was commissioned shortly after Kavango brought its 50-ton-per-day gold processing plant into operation, adding electricity infrastructure to the processing capacity already established at the site.

New capacity supports expansion plans 

Together, the processing plant, upgraded grid connection and existing backup generation capacity are intended to provide the infrastructure needed to support higher processing volumes. The additional transformer capacity also gives Kavango greater flexibility as it develops its gold production operations. 

CEO Jasper Musadaidzwa described the installation as another milestone in the company’s development of Hillside, highlighting the importance of reliable and affordable electricity to its production ambitions. 

“Increasing our installed transformer capacity fivefold to 1.25 MVA will enable us to supply grid electricity directly to our operations, which we expect will improve power supply stability and reduce our energy costs,” Musadaidzwa said. 

He added that the combination of grid electricity and backup generation would strengthen the foundation for existing operations and the company’s planned expansion of gold processing capacity.

Infrastructure moves beyond commissioning 

For Kavango, the latest investment moves Hillside’s development beyond the commissioning of its processing plant towards establishing the supporting infrastructure required for sustained operations. 

The company is now positioning electricity supply, processing capacity and backup generation as complementary parts of its production expansion strategy.